A77 Active Corridor logoA77 Active Corridor

Milestones

  • Phase 1 - Community Engagement

    October 2021

     

    -

     

    December 2021

    Gather thoughts on Detailed Design of Phase 1 improvements to active travel infrastructure along the A77 Ayr Road - between North Hillhead Street and the M77 overbridge - plus initial ideas for Phase 2.
  • Phase 1 - Construction

    January 2022

     

    -

     

    June 2022

    Construct Phase 1 improvements to active travel infrastructure along the A77 Ayr Road.
  • Phase 2 - Detailed Design

    March 2022

     

    -

     

    December 2022

    Develop Detailed Design of Phase 2 improvements to active travel infrastructure along the A77 Ayr Road, plus initial concepts for future phases (the "A77 Masterplan").
  • Phase 2 - Community Engagement

    June 2022

     

    -

     

    Complete

    Gather thoughts on Detailed Design of Phase 2 improvements to active travel infrastructure along Ayr Road - between the M77 overbridge and Malletsheugh roundabout.
  • Phase 2 - Construction

    February 2023

     

    -

     

    September 2023

    Construct Phase 2 improvements to active travel infrastructure along the A77 Ayr Road.
  • Phase 3 - Concept Design

    December 2023

     

    -

     

    January 2024

    Following a successful application for funding from Strathclyde Partnership for Transport, we have appointed engineering consultancy firm Sweco to develop Concept Design and Detailed Design for the section of the A77 (Ayr Road) between Hunter Drive and Barrhead Road.
  • Phase 3 - Community Engagement

    February 2024

     

    -

     

    Complete

    An opportunity to provide feedback on the Concept Design plans for Phase 3, to help shape the emerging Detailed Design plans.
  • Phase 3 - Detailed Design

    February 2024

     

    -

     

    March 2024

    Following a successful application for funding from Strathclyde Partnership for Transport, we have appointed engineering consultancy firm Sweco to develop Concept Design and Detailed Design for the section of the A77 (Ayr Road) between Hunter Drive and Barrhead Road.
  • Phase 5+ - Concept Design

    October 2023

     

    -

     

    April 2024

    Following a successful application for funding from the Sustrans Places for Everyone programme, we have appointed engineering consultancy firm AtkinsRéalis to develop initial concept designs for the section of the A77 (Ayr Road and Fenwick Road) between Crookfur Road and the Glasgow City Council boundary.
  • Phase 5+ - Community Engagement

    March 2024

     

    -

     

    In Progress

    Opportunities to see early design ideas for Phase 5+.
  • Phase 5+ - Detailed Design

    TBC

     

    -

     

    End date

    Detailed Design of Phase 5+ will progress subject to successful funding application(s) and necessary approvals.
  • Phase 3 - Construction

    TBC

     

    -

     

    End date

    Construction of Phase 3 will progress subject to successful funding application(s) and necessary approvals.
  • Phase 5+ - Construction

    TBC

     

    -

     

    End date

    Construction of Phase 5+ will progress subject to successful funding application(s) and necessary approvals. Due to the length of the route, it is likely that construction would be phased over a number of years.